Skyline Park

  • Park typeMini Park
  • Project statusConstruction
  • Project scheduleSummer - Fall 2023
  • Park size0.9 Acres
  • Special useNone

Current Status

The park is near completion. City crews will install picnic tables, benches and a bike rack in the month of March. The sitework contractor will return in April to install the basketball goals and stripe the new court. We appreciate the community’s patience during construction of the park improvements and we hope everyone is enjoying the new playground equipment with our early spring!

Updated March 12, 2024

Project Summary & Concept Plans

This mini park services a neighborhood with a high amount of underserved populations. It contains a popular full basketball court and playground with fencing around the perimeter and utilizes much of the park property.

Improvements

General recommendations includes redevelopment with some modifications to the layout to make the most of the park land available for an improved recreational experience.

Recommendations include:

  • Replace playground equipment meeting a broader range of challenge levels and age groups
  • ADA compliant playground surfacing
  • Add in specialty unique challenge or fitness area
  • Drinking fountain
  • New picnic shelter or unique shade structure
  • Reconstruct full basketball court further away from the playground and include artistic elements to backstop fencing to contain balls
  • Security light

Resources

Playground Design

Timeline

This project was completed in 2023.

Community Engagement

Beginning in 2019, the City undertook a comprehensive public engagement process through a variety of methods, allowing for a better understanding of current views, desires and trends related to parks, trails and recreation.

Engagement methods included:

  • Online outreach through Social PinPoint and Polco platforms
  • Four-part in-person visioning series conducted by the Twin Cities LISC's Corridor Development Initiative
  • Targeted outreach to specific project stakeholders including Fridley athletic associations, senior center and Fridley ISD 13
  • Gathered feedback through an interactive, GIS-based story map project website
  • Targeted community outreach through pop-up events
  • Community survey conducted by The Morris Leatherman Company

An in-park community meeting was held on Tuesday, August 16 to allow residents to vote on playground equipment and discuss the project with City staff. Residents who could not make it to the meeting had the opportunity to give feedback via an online survey. The feedback will help decide what equipment to order for construction in 2023.

Funding Source

A total of $50 million in possible park system improvements were identified in the Park Plan. Based on resident input, Fridley City Council directed staff to work with a Park Plan Refinement Task Force advisory group to recommend $30 million in park projects that would be most impactful to the community.

Further, a resident Finance Task Force recommended funding the park system improvement plan by issuing General Obligation (GO) Tax Abatement Bonds for $20 million in bond proceeds, being repaid over no more than 15 years, with an additional $10 million to come from other City of Fridley funds.

Tax abatement is a tool that can be used by cities to abate all or a portion of property taxes levied by the City for a given purpose, such as public infrastructure improvements. All taxpayers, whether identified as an abated parcel or not, will continue to pay property taxes as they normally would. Minnesota Statute 469.1813 gives cities authority for tax abatement, and this has become an increasingly common means of funding park improvements, as they provide benefit to all residents. A requirement is holding a public hearing for the consideration of tax abatement, and that was held on May 23, 2022.The bonds will be repaid over 15 years with annual debt service payments being levied for and it is likely there will be an increase in property taxes beginning in 2023.

This plan will provide many opportunities for expanded recreation programming, enjoyment of nature and social gatherings. Enhancing and modernizing the city park system will position Fridley as a great place to live, work and play now and for many years to come.

Project Contacts

Questions about the project? Please email ParkPlan@FridleyMN.govwith questions or concerns.

Location

5880 2nd Street, Fridley, MN 55432  View Map